General contractor and maintenance
BP STEAM at the refinery site Gelsenkirchen-Scholven, Germany
Iqony was hired by ROG as EPC for the planning, construction, commissioning and subsequent maintenance of 4 new high-pressure steam boilers with a total maximum rated thermal output of 436 MWth.
After completion of the high-pressure steam boilers, Iqony Solutions is responsible as a subcontractor for the maintenance measures for all four boilers, including all ancillary systems for a period of 5 years from the commissioning of the last boiler.
IQS provides the following services:
- Scheduled and unscheduled maintenance
- Delivery of spare and wear parts
- Consumables
- Warehouse responsibility
- Evaluation of operating data for preventive maintenance
Iqony Solutions | Services for energy plants | O&M, engineering & IT solutions
Project facts
| Installed capacity |
|
| Technology | Natural circulation boiler |
| Fuel | Natural gas / coke gas / refinary gas |
| Customer | Iqony GmbH / Ruhr Oel GmbH |
| IQS performance period | 5 years |